Since 21 October 2026, householders in England without a driveway can often install a home charge point without a planning application, and councils can put cable channels into the pavement without one. But the limits are tight, and highway consent and building regulations still apply.
planningengland

Until this autumn, the national planning rules for home electric vehicle charge points in England were written around off-street parking. If you had a drive or a garage, a wall-mounted charger was usually permitted development. If you parked on the street, there was no equivalent right. A change that came into force on 21 October 2026 addresses part of that gap. This guide covers England only and is general information, not legal advice. Check your own position with your local planning authority and highway authority before work starts.
What changed on 21 October 2026
The Town and Country Planning (General Permitted Development) (England) (Amendment) (No. 2) Order 2026 was made on 25 September 2026 and came into force on 21 October 2026. For householders it does three things. It widens Class D of Part 2 of the General Permitted Development Order (GPDO), which covers wall-mounted charge points, and Class E, which covers charge points on an upstand, such as a post. And it creates a new Class F in Part 9 for "cross-pavement solutions": cable channels set into the pavement so a charging cable can reach a car parked on the road.
The Department for Transport announced the change on 21 October 2026, saying it would save drivers up to £300 on installation by removing the need for planning permission for cross-pavement chargers. That figure is the government's own estimate; actual savings will depend on the council and the installation.
Wall-mounted charge points: the new Class D
Under the amended Class D, permitted development now covers installing, altering or replacing a wall-mounted charging outlet either within an area lawfully used for off-street parking, or within any other area within the curtilage of a house or block of flats. The second limb is what helps households without a drive. Several limits apply:
- The outlet and its casing must not exceed 0.2 cubic metres, and must not be installed more than 1.6 metres above ground level.
- It must not be within the curtilage of a listed building or on a site designated as a scheduled monument.
- Where the outlet is not in an off-street parking area, only one outlet is allowed within the curtilage, and the right does not apply in a conservation area.
- If the outlet is mounted on a wall that immediately adjoins a highway, it must not protrude more than 0.2 metres from the wall, and there must be at least 1.5 metres' width of footway between its outermost point and the edge of the carriageway.
There are also conditions. The charge point must be removed when it is no longer needed for charging, and the wall reinstated as far as reasonably practicable. And where there is a footway between the outlet and the car, the charging cable must cross it by means of an authorised cross-pavement solution while it is in use. A cable laid loose across the pavement does not meet that condition.
Charge points on posts: Class E
Class E now also covers an upstand with a charging outlet within any area within the curtilage of a house or block of flats, as well as in off-street parking areas. In a domestic setting the upstand and outlet must not exceed 1.6 metres in height from the parking surface, there can be no more than one upstand for each parking space, and the same exclusions for listed buildings and scheduled monuments apply. Outside off-street parking areas, the right does not apply in a conservation area. The same cable condition applies where a footway lies between the upstand and the car.
Cable channels in the pavement: the new Class F
Article 7 of the Order adds Class F to Part 9 of the GPDO. It grants planning permission for the installation, alteration or replacement of a cross-pavement solution "by, on behalf of, or with the authorisation of, a highway authority". A cross-pavement solution is defined as a pavement-embedded cable channel that allows a charging cable to cross a footway safely from a home to a parked vehicle. The right does not apply in a conservation area, within the curtilage of a listed building or on a scheduled monument, and the channel must be removed and the pavement reinstated when it is no longer needed.
In practice, this means a householder cannot simply have a channel cut into the pavement. The highway authority has to install it, have it installed on its behalf, or authorise it. The government's guidance on cross-pavement solutions, updated on 4 November 2026, says the decision to allow an installation in the public highway rests with the relevant local authority, and that the suitability of each location depends on the factors the guidance sets out.
Other consents you may still need
Planning permission is only one of the permissions involved. The guidance lists others that may be needed, depending on the ownership model the council uses:
- permission under section 178 of the Highways Act 1980;
- a licence under section 50 of the New Roads and Street Works Act 1991, or a street works permit;
- a traffic regulation order.
Where a road has not been adopted by the highway authority, the guidance says the resident should seek permission from the landowner instead. It describes two ownership models: the council owns and maintains the channel, or a supplier does. Where there are two tiers of local government, the highway authority will generally be the upper tier and the planning authority the lower tier, so you may deal with two bodies. The guidance also notes that this infrastructure is not generally accompanied by any reserved parking.
Building regulations still apply
The planning change does not affect the Building Regulations. The Planning Portal says installing a home charger is notifiable work because it involves creating a new circuit. That follows regulation 12(6A) of the Building Regulations 2010, which requires a building notice or an application with full plans for work under Part P that consists of installing a new circuit, unless an exemption applies. An electrician registered with a competent person scheme can self-certify the work and issue a compliance certificate; otherwise building control must be notified. Keep the certificate with your property papers: our guide to building regulations sign-off explains why it matters when you sell.
When you will still need planning permission
If a proposal falls outside the permitted development limits, you can apply for planning permission. The Planning Portal says permission is usually needed in conservation areas, for listed buildings, where an Article 4 direction restricts charge points, and for more than one upstand per parking space. Our guides to conservation areas and Article 4 directions and the householder application process explain the steps. If you want formal confirmation that a charger is lawful, a Lawful Development Certificate is optional but can help when you sell.
The Order includes a transitional provision: development that was permitted under the old Classes D or E immediately before 21 October 2026, but is no longer permitted under the new wording, can still be carried out until the end of 20 October 2027.
Grants and consultations
The government's EV chargepoint grant for renters or flat owners offers 75% off the cost of buying and installing a socket, up to £500. According to the eligibility rules, it is for people who own a flat or rent a home, and you must have your own private off-street parking space; owners of houses cannot apply. The Department for Transport also has two consultations open until 16 December 2026: one on amending the building regulations on charging infrastructure, and one on expanding charging access for tenants and leaseholders. Our guide to energy upgrade grants covers other home energy schemes.
Before you start
Check whether your home is listed or in a conservation area, and whether an Article 4 direction applies. If you have no driveway, ask your council whether it has a cross-pavement scheme and who will own and maintain the channel. Then use a registered electrician for the charge point. If the work is part of a wider project, such as new paving or an extension, you can request quotes from independent builders. Home Builders does not carry out building work: we ask advertisers to provide proof of insurance, and any contract is between you and the builder you choose.
Sources: Town and Country Planning (General Permitted Development) (England) (Amendment) (No. 2) Order 2026 (SI 2026/1056), including article 7 and article 10; GPDO 2015, Schedule 2, Part 2 (as amended); DfT and OZEV: cross-pavement solutions for charging electric vehicles; DfT press release, 21 October 2026; Planning Portal: EV charging, building regulations; Planning Portal: EV charging, planning permission; Building Regulations 2010, regulation 12; GOV.UK: EV chargepoint grant for renters or flat owners.
Frequently asked questions
Do I need planning permission for a home EV charger if I have no driveway?
Often not, since 21 October 2026. Permitted development now covers one wall-mounted charge point within the curtilage of a house or block of flats without off-street parking, subject to size and height limits. It does not apply in conservation areas or to listed buildings.
Can I run a charging cable across the pavement?
Only through an authorised cross-pavement solution. The new rules require the cable to cross the footway in a pavement-embedded channel installed by, on behalf of, or with the authorisation of the highway authority. A loose cable does not meet the condition.
Do building regulations apply to a home charge point?
Yes. The Planning Portal says installing a home charger is notifiable work because it involves a new circuit. A registered competent person can self-certify it; otherwise building control must be notified before work starts.
Does the new right apply in a conservation area?
Not for homes without off-street parking. The new routes for chargers outside off-street parking areas, and the new Class F for pavement channels, do not apply in conservation areas, so check with your local planning authority.