Building over or near a public sewer in England: build over agreements and Part H4 explained

Many extensions are built close to a shared sewer without the homeowner realising it is public. Planning permission does not cover building over it. Water companies usually expect an application when work is within 3 metres, and building control must check Part H4.

By the Home Builders editorial team · Published · Last reviewed

planningengland

Grey corrugated drainage pipe bedded on gravel in a freshly dug trench between banks of dry brown earth
Photo: D Goug / Pexels

Sewers often run under back gardens, especially in towns and cities, and a rear or side extension can easily end up on top of one. If the pipe is a public sewer or a public lateral drain, it belongs to the local water and sewerage company, and you will usually need its approval before you build over or near it. This guide covers England only and is general information, not legal or engineering advice. Check the position for your own property with your water company and building control before you finalise a design.

Public sewers, lateral drains and private drains

A drain that serves only your property and runs within your boundary is generally your responsibility. Once pipes serve more than one property, or run beyond the boundary, they are often public. The Water Industry (Schemes for Adoption of Private Sewers) Regulations 2011 required sewerage companies to adopt most private sewers and lateral drains that connected to the public network, with a vesting date of 1 October 2011. As a result, many shared pipes in older gardens became public.

Thames Water explains the difference simply: it is responsible for public sewers and public lateral drains in its region, while private drains are the responsibility of the landowner. A lateral drain is the length of pipe serving one property that lies outside its boundary, typically running to the sewer under the road or a neighbour's garden.

What Part H4 of the Building Regulations requires

Requirement H4 in Schedule 1 to the Building Regulations 2010 says that the erection or extension of a building, or work involving underpinning, must be carried out in a way that is not detrimental to the building or extension, or to the continued maintenance of the drain, sewer or disposal main. It applies to work over a drain, sewer or disposal main shown on a "map of sewers", meaning the records a sewerage undertaker keeps under section 199 of the Water Industry Act 1991, and to work that could interfere with the use of, or obstruct access to, such a pipe.

The official guidance is in Approved Document H (2015 edition). Its H4 section applies to building over or within 3 metres of the centreline of a drain, sewer or disposal main shown on the sewer records, public or not. Among other points, it says:

  • buildings or extensions should not be built over a manhole, inspection chamber or other access fitting on a sewer serving more than one property, unless an alternative access point acceptable to the owner can be provided;
  • the length of drain or sewer under a building should not exceed 6 metres, except with the owner's permission;
  • buildings should not be built over or within 3 metres of a drain or sewer more than 3 metres deep, or more than 225mm in diameter, except with the owner's permission;
  • a satisfactory diversionary route should be available, so the pipe could be rebuilt without affecting the building;
  • special measures are expected near rising mains, brick or masonry sewers and pipes in poor condition, and in easily eroded soils such as fine sands, saturated silts and peat;
  • where a pipe more than 2 metres deep to invert passes beneath the foundations, the foundations should be designed as a lintel spanning at least 1.5 metres either side of the pipe, so no load is transmitted onto it.

For a public sewer, Approved Document H notes that the owner is the sewerage undertaker, and that any repair or replacement of a public sewer will be carried out by the undertaker.

How building control and the water company fit together

If you make a full plans application and Part H4 applies, regulation 15 of the Building Regulations 2010 requires the building control body to consult the sewerage undertaker as soon as practicable, and again before issuing a completion certificate. It must have regard to the undertaker's views, and it must not grant approval or issue a completion certificate until 15 days have passed from consulting, unless the undertaker has already responded.

That consultation is not the same as the water company's own consent. Thames Water states that planning permission does not grant you permission to build over a sewer or drain, and that you should not start building before you have an agreement. Southern Water's build over guidance notes add that you still need its approval even if your work is exempt from building regulations.

When water companies expect an application

Each company sets its own process, forms and fees, so check with the one that serves your address. As examples, Thames Water says you are likely to need to apply if you build within 3 metres of a public sewer or within 1 metre of a public lateral drain. United Utilities says you need its approval to build over or close to its sewers or lateral drains, usually within 3 metres, even if the pipe is on your land, and that it often prefers a diversion.

Many companies offer two routes. Smaller, simpler projects may qualify for self-certification, while others need a formal build over agreement. Severn Trent, for example, says its formal route applies if the sewer is larger than 150mm, if you need to move, alter or build over a manhole, or if the project does not meet its self-certification requirements. It describes a review of up to 10 working days, then a provisional approval with conditions, and a CCTV survey report after the work is finished. Southern Water says a CCTV survey may be needed to establish the condition and position of the sewer.

Your options if a sewer is in the way

Southern Water's guidance sets out the practical choices. You can change the design so the building is at least 3 metres from the sewer, which it calls often the cheapest and easiest option. You can apply to divert the sewer, which needs the water company's agreement. Or you can apply to build over or near it. Thames Water says liability for any damage caused to the sewers or drains during construction lies with you.

A practical checklist

  1. Find out where the pipes run before the design is fixed. Sewer records must be available for public inspection free of charge at an office of the sewerage undertaker under section 199 of the Water Industry Act 1991, and a builder or drainage specialist can survey the pipes on your land.
  2. Note manholes and inspection chambers. Building over one that serves other properties is usually the hardest case.
  3. Contact your water company early and ask which route applies, what it will cost and how long it takes.
  4. Tell your designer and building control about any sewer within 3 metres, so foundations can be designed to Part H4.
  5. Do not start work on the affected section until you have written approval.
  6. Keep the water company's approval with your completion certificate and other project paperwork.

Other consents may still apply. Your project may need planning permission or fall under permitted development, and work on or near a shared wall may need a party wall notice. Our garden rooms guide covers outbuildings. If work has already been done without building regulations approval, see our guide to regularisation certificates.

When your plans are settled, you can request quotes from independent builders. Home Builders does not carry out building work: we ask advertisers to provide proof of insurance, and any contract is between you and the builder you choose.

Sources: Building Regulations 2010, Schedule 1 (Part H4); regulation 15; Approved Document H (2015 edition); Water Industry Act 1991, section 199; Water Industry (Schemes for Adoption of Private Sewers) Regulations 2011, regulation 3; Thames Water: build over agreements; United Utilities: building over a public sewer; Severn Trent: building over or near our sewer pipes; Southern Water: build over guidance notes.

Frequently asked questions

Do I need a build over agreement for my extension?

Possibly. Water companies commonly expect an application if you build within 3 metres of a public sewer, and Thames Water also mentions work within 1 metre of a public lateral drain. Rules, forms and fees differ between companies, so check with the one that serves your address.

Does planning permission cover building over a sewer?

No. Thames Water states that planning permission does not grant permission to build over a sewer or drain. Building control must also consider Part H4 of the Building Regulations, and the water company's approval is separate from both.

How do I find out where the public sewers are?

Sewerage companies must keep sewer records and make them available for public inspection free of charge at one of their offices under section 199 of the Water Industry Act 1991. A builder or drainage specialist can also survey the pipes within your property.

Can I build over a manhole?

Approved Document H says extensions should not be built over a manhole or inspection chamber on a sewer serving more than one property, unless an alternative access point acceptable to the owner is provided. Severn Trent, for example, requires its formal application if you need to move, alter or build over a manhole.

Advertising disclosure: Home Builders is funded by builders who advertise with us. Advertisers have no say over our guides, and listing is not an endorsement. Read our editorial policy.

Request quotes · UK introductions

Get matched with a local builder

Tell us about your extension, loft or renovation anywhere in the UK. With your consent, we pass your enquiry to up to 3 independent builders who advertise with us, so they can contact you with quotes. We do not carry out building work ourselves.

  • Free to use, no obligation
  • Up to 3 builders, only with your consent
  • Always check each builder’s insurance, references and written quote
About you

Optional. Add it only if you're happy for the builders we pass your enquiry to to call you.

Your project

Please don't include bank, payment or health details.

Budget & timing

Builders listed on Home Builders are independent businesses. We ask every builder who advertises with us to provide proof of current public liability insurance before they are listed. Always check each builder's insurance, references, written quote and trade body membership yourself before work starts. Forms are processed on homebuilders.co.uk.