Part L energy standards for house extensions in England: what applies now and from March 2027
Extensions, loft conversions and replacement windows in existing homes have to meet energy efficiency standards in Part L of the Building Regulations. A new Approved Document takes effect on 24 March 2027, but the current limiting U-values for new walls, roofs, floors and windows in existing dwellings stay the same.
planningenglandextensions

Most extensions, loft conversions and new or replacement windows in an existing home have to meet energy efficiency requirements in Part L of the Building Regulations. This guide covers England only and is general information, not legal or technical advice. The Approved Documents are statutory guidance on one way to meet the requirements, not a substitute for the regulations themselves. Speak to your building control body, or a qualified designer, about your own project.
What Part L covers in an existing house
Part L of Schedule 1 to the Building Regulations 2010 deals with the conservation of fuel and power. For work to existing dwellings, the current statutory guidance is Approved Document L, Volume 1: Dwellings, 2021 edition incorporating 2023 amendments. Section 10 of that document covers new elements in existing dwellings, including extensions, replacement windows and doors, and adding a conservatory or porch.
Building regulations approval is separate from planning permission. Our guide to full plans and building notice applications explains how to apply before work starts, and our guide to completion certificates explains sign-off at the end.
The standards that apply now
The 2021 edition, with the 2023 amendments, is the current guidance for work that is not yet under the 2026 standards. For new fabric elements in existing dwellings, including extensions, Table 4.2 sets these maximum U-values, in W/(m2·K):
- roof: 0.15
- wall: 0.18
- floor: 0.18
- window: 1.4, or a Window Energy Rating of Band B or better
- rooflight: 2.2
- doors with more than 60 per cent of the internal face glazed: 1.4, or a Doorset Energy Rating of Band C or better
- other doors: 1.4, or a Doorset Energy Rating of Band B or better
Those wall, roof and floor figures are area-weighted averages. Windows, doors, roof windows and rooflights are assessed individually. The table also allows a maximum of 1.8 W/(m2·K) for external fire doorsets, as defined in Approved Document B, Volume 1. Notes to the table set out limited cases in which a lesser standard may be appropriate, for example if meeting the wall figure would cut the internal floor area of a room by more than 5 per cent, or if the floor figure would cause significant problems with adjoining floor levels.
How much glazing an extension can have
When a dwelling is extended, paragraph 10.7 says new thermal elements and new windows, roof windows, rooflights and doors should meet Table 4.2, and the total area of those openings in the extension should not exceed 25 per cent of the floor area of the extension plus the area of any windows and doors that no longer exist, or are no longer exposed, because of the extension. Existing fabric that becomes a thermal element, such as a wall that used to be internal, should be upgraded following the guidance on retained elements.
There are two official alternatives to meeting paragraph 10.7 element by element. Paragraph 10.9 allows an area-weighted U-value calculation for the extension as a whole, compared with an extension of the same size and shape that would comply with paragraph 10.7. Paragraph 10.10 allows the Standard Assessment Procedure to be used to show that the dwelling plus the proposed extension would be no worse, on the dwelling primary energy rate, emission rate and fabric energy efficiency rate, than the dwelling plus a notional extension that complies with paragraph 10.7.
Loft conversions and retained elements
If you convert a loft or a garage, elements that are retained and become thermal elements are covered by Table 4.3, not Table 4.2. Where the existing U-value is worse than the threshold in column (a), the guidance is to upgrade to the improved value in column (b) where that is technically and functionally feasible and would achieve a simple payback of 15 years or less. The improved values include 0.16 for a roof, 0.30 for a wall with internal or external insulation, 0.55 for a wall with cavity insulation, and 0.25 for a floor. Our guide to loft conversion regulations covers the wider planning and fire-safety rules that also apply.
Conservatories, porches and historic buildings
Under regulation 21 of the Building Regulations, adding a conservatory or porch is exempt from the energy efficiency requirements if all of the conditions in paragraph 0.14 are met: it is at ground level, its floor area does not exceed 30m2, the glazing complies with Part K, any separating wall, door or window is retained or replaced, and the dwelling's heating system is not extended into it. If the thermal separation is removed or the heating system is extended, Approved Document L says the conservatory or porch should be treated as an extension. Our guide to garden rooms and outbuildings covers the separate planning and building-regulations questions that arise for other garden buildings.
New extensions to historic and traditional dwellings should, under paragraph 0.11, comply fully with the energy efficiency standards unless there is a need to match the appearance or character of the host building, in which case the work should comply to the extent that it is reasonably practicable.
What changes on 24 March 2027
The government published a new Approved Document L, 2026 edition on 24 March 2026. The document itself says it takes effect on 24 March 2027 in England for building work that is not in connection with higher-risk building work, and on 24 September 2027 for building work that is in connection with higher-risk building work. Full details of the transitional arrangements are in Building Circular 01/2026, which accompanies the Building Regulations etc. (Amendment) (England) Regulations 2026.
For ordinary (non-higher-risk) work, the circular says the changes will not apply where a building notice, an initial notice, or an application for building control approval with full plans has been given to the relevant authority before 24 March 2027, provided the work is commenced, as defined in the regulations, before 24 March 2028. Most house extensions are not higher-risk building work, which is defined by height and use for the Building Safety Regulator's regime.
For householders, the important practical point is this: Table 3.2 of the 2026 edition, which will replace Table 4.2 for new fabric elements in existing dwellings, uses the same limiting U-values for roofs, walls, floors, windows, rooflights and doors. The 25 per cent openings rule and the alternative calculation routes are also carried forward, with the paragraph numbers rearranged. The 2026 changes are more significant for new dwellings, heat pumps, on-site renewable electricity when a dwelling is erected, and other building services. If you are planning an extension around the 2027 commencement date, the transitional rules above decide which edition your job falls under.
What to do next
Ask your designer or builder to show how the extension or conversion will meet the current Table 4.2 standards, or one of the official alternative methods, and apply for building regulations approval before work starts. Replacement windows that are installed as complete units are controlled fittings and should also meet Table 4.2. Grants for energy-efficiency work, which are a separate matter from the legal standards, are described in our guide to energy upgrade grants.
If you want help finding a builder, you can request quotes from independent builders. Home Builders does not carry out building work: we ask advertisers to provide proof of insurance, and any contract is between you and the builder you choose.
Sources: GOV.UK: conservation of fuel and power, Approved Document L; Approved Document L, Volume 1: Dwellings, 2021 edition incorporating 2023 amendments (PDF), including Table 4.2, Table 4.3 and Section 10; GOV.UK: Approved Document L, 2026 edition; Approved Document L, Volume 1: Dwellings, 2026 edition (PDF), including Table 3.2; The Future Homes and Buildings Standards: Building Circular 01/2026; The Building Regulations etc. (Amendment) (England) Regulations 2026; The Building Regulations 2010.
Frequently asked questions
What U-values does an extension in England have to meet?
Under the current Approved Document L, Volume 1 (2021 edition with 2023 amendments), new fabric in an existing dwelling should meet Table 4.2: 0.15 for roofs, 0.18 for walls and floors, 1.4 for windows (or Window Energy Rating Band B or better), 2.2 for rooflights and 1.4 for doors, with the official energy-rating alternatives. The figures are in W/(m²·K).
Do the rules change in March 2027?
A new Approved Document L takes effect on 24 March 2027 for work that is not higher-risk building work, subject to transitional arrangements in Circular 01/2026. For new walls, roofs, floors and windows in existing dwellings, the limiting U-values in the 2026 edition's Table 3.2 are the same as today's Table 4.2.
Does a conservatory have to meet Part L?
Not if it meets all the exemption conditions in paragraph 0.14, including a floor area of no more than 30m², thermal separation from the house, and no extension of the dwelling's heating system into the conservatory. If that separation is removed or the heating is extended, it should be treated as an extension.
Is planning permission the same as Part L?
No. Planning permission and building regulations are separate. An extension may be permitted development for planning purposes and still need building regulations approval, including compliance with Part L.