Planning conditions explained: how householders discharge them, change them and avoid enforcement in England

A grant of planning permission is rarely the end of the paperwork. Most decision notices carry conditions, and some must be dealt with before a spade goes in the ground. Here is how conditions work, how to get them signed off or changed, and what can happen if they are ignored.

By the Home Builders editorial team · Published · Last reviewed

planningengland

New blockwork walls with render mesh and a white window on a house extension, with metal scaffolding
Photo: Brett Jordan / Pexels

When a council grants planning permission for an extension, loft dormer or garden building, the decision notice almost always lists conditions. This guide covers England only and is general information, not legal or planning advice. Check the wording of your own decision notice with your council's planning service, or a planning professional, before you rely on it.

Why councils attach conditions

Under section 70 of the Town and Country Planning Act 1990, a council granting permission may impose "such conditions as they think fit". Government planning practice guidance on the use of conditions explains that, used properly, conditions allow development to go ahead where it would otherwise have to be refused, by dealing with its adverse effects.

That power is not unlimited. National policy says conditions should be kept to a minimum and used only where they meet six tests: they must be necessary, relevant to planning, relevant to the development permitted, enforceable, precise and reasonable in all other respects. The guidance says a condition that fails any one of the tests should not be used, even if the applicant agrees to it.

The main types of condition

The time limit

Every full permission has a deadline for starting work. Under section 91 of the 1990 Act, development must begin within 3 years of the date of the permission, unless the council sets a different period. If the permission lapses, you will normally need to apply again. Our guide to householder planning applications explains the application process.

Approved plans and compliance conditions

Many conditions simply require the work to follow the approved drawings, or set a rule that applies once the work is built, for example about materials, window glazing or the use of a garden building. These do not need a separate application, but they must be complied with, and they continue to apply after the builders have left.

Conditions that need further approval

Other conditions require you to submit details for the council's approval, such as samples of facing materials or a drainage scheme. These are the conditions that have to be discharged.

Pre-commencement conditions

Conditions worded "no development shall take place until..." are pre-commencement conditions. Since the section 100ZA rules took effect, a council in England cannot grant permission subject to one without the applicant's written agreement to its terms, except in circumstances set out in regulations. The guidance warns that development carried out without complying with a pre-commencement condition would be unlawful and may be the subject of enforcement action.

How to discharge a condition

Under article 27 of the Development Management Procedure Order 2015, a request for approval of details required by a condition must be made in writing, must identify the planning permission and must include the plans and information needed to deal with it. GOV.UK says the standard application form for approval of details reserved by a condition must be used. You can usually apply through the Planning Portal or your council's own form.

  • One request can cover several conditions. The fee is charged per request, not per condition.
  • Decision period. The council must give its decision within 8 weeks, beginning with the day after it receives the request, or any longer period agreed in writing.
  • Fee refund. The guidance says that if no decision is made within 12 weeks, the council must return the fee without further delay.
  • Partial outcomes. Some councils, such as Tendring District Council, explain that where a request covers several conditions they may approve some and refuse others.

Fees before and after 8 December 2026

The fee to discharge conditions on a householder permission is £89 per request, according to the Planning Portal's fee schedule from 1 April 2026. The Town and Country Planning (Fees for Applications, Deemed Applications, Requests and Site Visits) (England) (Amendment and Transitional Provision) Regulations 2026, made on 10 November 2026, come into force on 8 December 2026. The government's fee table from that date sets the householder discharge fee at £125 for requests made on or after that date. Requests made before it pay the current fee. The Planning Portal's own service charge applies only to online applications with a statutory fee over £100, so a request at £89 does not attract it, but one at £125 from 8 December 2026 may, depending on the Portal's charging band. Check the Planning Portal's fee information before you apply online. Some councils, including Mid Suffolk District Council, say there is no fee to discharge conditions on a listed building consent. Our guide to the December 2026 fee changes covers the other householder fees.

Deemed discharge

If a council is slow, the applicant may be able to serve a deemed discharge notice under articles 28 to 30 of the 2015 Order. The guidance says a notice can be served once at least 6 weeks have passed since the council received the request, or a shorter agreed period. The date in the notice must be no earlier than the end of the normal decision period, and no earlier than 14 days after the day following the one on which the council receives the notice. If the council has still not decided by that date, the condition is treated as discharged. Deemed discharge cannot be used for the types of condition listed in Schedule 6 to the Order, or where the applicant and council have agreed in writing that it will not apply, so check before relying on it.

Changing a permission or its conditions

Non-material amendments

Small changes, such as a minor adjustment to a window, may be possible through a non-material amendment under section 96A. The government's guidance on flexible options for planning permissions says there is no statutory definition of "non-material", because it depends on the scheme as a whole. Anyone who owns the land affected must be notified first and has 14 days to comment. The council has 28 days to decide, unless a longer period is agreed. There is no right of appeal against a refusal, and the procedure cannot be used for listed building consents. The householder fee is £46 for applications made before 8 December 2026 and £53 for applications made on or after that date.

Varying or removing a condition (section 73)

An application under section 73 can vary or remove conditions. Where the permission has a condition listing the approved plans, it can also be used to make minor material amendments. The guidance explains that a successful application creates a new, independent permission alongside the original one. Section 73 cannot extend the time limit for starting work or change the description of the development. A refusal can be appealed. The householder fee is £89 for applications made before 8 December 2026 and £112 for applications made on or after that date.

Appealing against a condition

GOV.UK confirms that you can appeal if you were granted permission with conditions you object to. The planning practice guidance says that for householder applications the appeal must be received within 12 weeks of the date on the decision notice (6 months for other decision types), and warns that the Inspector will decide the whole application again, not only the disputed condition, so there is a risk that permission could be refused altogether.

If conditions are not complied with

A council can serve a breach of condition notice under section 187A, setting out the steps needed to comply. The notice must allow at least 28 days for compliance. Failing to comply with a breach of condition notice is a criminal offence (section 187A(9)). The guidance also notes that retrospective planning permission can be sought under section 73A. Unresolved conditions can come to light when a property is sold, so keep every decision notice and discharge letter with your other property records.

A practical checklist

  1. Read every condition on the decision notice and sort them into pre-commencement, before occupation or use, and ongoing compliance conditions.
  2. Submit details for any pre-commencement condition early, allowing for the 8-week decision period.
  3. Do not start work that a pre-commencement condition covers until the council has confirmed in writing that the condition has been dealt with, and ask the council if you are unsure.
  4. If the design changes, ask the council whether a non-material amendment, a section 73 application or a new application is the right route before building it.
  5. Remember that planning conditions are separate from building regulations: see our guide to full plans and building notices, and to getting a completion certificate.
  6. Serve any notices needed under the Party Wall etc. Act 1996.

If your project falls within permitted development instead, there may be no planning conditions to discharge, although prior approval and permitted development rights carry their own limits and conditions, and a Lawful Development Certificate can confirm the position.

When your conditions are in hand, you can request quotes from independent builders. Home Builders does not carry out building work: we ask advertisers to provide proof of insurance, and any contract is between you and the builder you choose.

Sources: MHCLG planning practice guidance: use of planning conditions; MHCLG planning practice guidance: flexible options for planning permissions; MHCLG: fees for planning applications; GOV.UK: appeal against a planning decision; Town and Country Planning Act 1990 (sections 70, 73, 73A, 91, 96A, 100ZA and 187A); Town and Country Planning (Development Management Procedure) (England) Order 2015 (articles 27 to 30 and Schedule 6); SI 2026/1192, planning fees amendment regulations 2026; MHCLG: fees for planning applications in England from 8 December 2026; Planning Portal: fees for planning applications in England from 1 April 2026; Planning Portal: what it costs; Tendring District Council: conditions discharge and compliance; Mid Suffolk District Council: discharge of conditions FAQs.

Frequently asked questions

What does discharging a planning condition mean?

It means getting the council's written approval of details that a condition requires, such as materials or a drainage scheme. You apply in writing with the details, and the council must normally decide within 8 weeks.

Can I start building before conditions are discharged?

Not if any condition is a pre-commencement condition, such as one worded “no development shall take place until...”. Government guidance says development carried out without complying with a pre-commencement condition would be unlawful and may face enforcement action.

How much does it cost to discharge conditions on a house extension?

£89 per request for householder development under the fees in force since 1 April 2026, rising to £125 for requests made on or after 8 December 2026. One request can cover several conditions, and the Planning Portal's separate service charge applies only to online applications with a statutory fee over £100, so check its fee information before you apply online.

What if I want to change my approved plans?

A small change may be possible as a non-material amendment, which the council has 28 days to decide. A bigger change may need a section 73 application to vary the approved plans condition, or a new planning application. Ask your council which route applies before building the change.

Advertising disclosure: Home Builders is funded by builders who advertise with us. Advertisers have no say over our guides, and listing is not an endorsement. Read our editorial policy.

Request quotes · UK introductions

Get matched with a local builder

Tell us about your extension, loft or renovation anywhere in the UK. With your consent, we pass your enquiry to up to 3 independent builders who advertise with us, so they can contact you with quotes. We do not carry out building work ourselves.

  • Free to use, no obligation
  • Up to 3 builders, only with your consent
  • Always check each builder’s insurance, references and written quote
About you

Optional. Add it only if you're happy for the builders we pass your enquiry to to call you.

Your project

Please don't include bank, payment or health details.

Budget & timing

Builders listed on Home Builders are independent businesses. We ask every builder who advertises with us to provide proof of current public liability insurance before they are listed. Always check each builder's insurance, references, written quote and trade body membership yourself before work starts. Forms are processed on homebuilders.co.uk.